| Main Contractor | Tungabhadra Right Canal Aquaduct |
|---|---|
| Scope of Work | Cast-in-Situ Piles, Steel Reinforcement |
| Number of Piles | 70 Piles |
| Pile Diameter | 1000 mm, |
| Total Pile Depth | --- |
| Equipment Used | Sany SR155 Piling Rig JCB 220, 140 Excavators, tippers, Tata Flat Bed Trailer |
| Year | March 2023 - Present |